In February 2008, Prime Minister Hun Sen laid the foundation.
In October 2008, the first plant was built and the first
enterprise settled in.
In January 2010, Hun
Sen Avenue was completed.
In July 2010, the first
department of one-stop service settled in.
In November 2011, the
comprehensive service center building opened.
In 2013, SSEZ connected
to the provincial transmission grid instead of diesel power.
In June 2016, SSEZ introduced
exactly 100 enterprises.
In February 2017, the
sewage treatment plant in SSEZ was officially operated.
In July 2017, the Fire
Station was opened in SSEZ.
In September 2017, the
Health Service Center was officially operated.
In January 2018, the
Neighborhood Center was put into use.
In March 2018, Preah
Sihanouk Cambodia-China Friendship Polytechnic Institute began enrolling
students.
In May 2019, the
thermal power plant in SSEZ started construction.
In December 2019, the
50MW high-voltage substation officially supplied power to SSEZ.
In December 2019, Sihanoukville
Institute of Business and Technology was officially opened.
In June 2020, 6
dormitory buildings for 1st phase were completed and put into use.
In December 2022, the thermal power plant stared operation.
|